Set the scope for an operational technology security review

Agree permitted assessment methods, maintenance windows and stop conditions with the plant operator before commissioning a security review.

Swiss Cyber Security18 min readPractical readingStart reading ↓

Short answer

Scope an operational technology security review with the plant operator before any assessment begins. Name the authorised systems, assessment methods, maintenance window, and conditions that stop the work. Start with plant safety and continuity requirements so the reviewer knows what records can be examined and when the operator must intervene.

Before you ask for a quote for an operational technology (OT) security review, agree the brief with the people who run the plant. Give them the list of systems and records, the proposed methods, and the conditions under which the reviewer must stop. The signed brief should let the shift supervisor decide whether work can start on the day. It should also let the reviewer recognise when a request, a new file, or a change in production takes the work outside that approval.

Start with the decision you need to make. If a packaging line depends on a supplier for recovery, you may need to know whether the plant has a recent, attributable configuration copy and who can account for changes made since it was saved. That is a question the reviewer can investigate through records. The brief should say which line, which records, what period, and what level of confidence the plant needs before deciding whether to commission further work.

Agree the decision and who has authority

Ask the operator what the process must keep doing while the review takes place. Discuss worker safety, product quality, production continuity, and the availability of staff who respond to an alarm. A packaging line may be idle while refrigeration, cleaning, and other lines continue to operate. A review that uses no plant equipment can still compete for the shift supervisor’s attention at the wrong time. NIST’s guide to OT security describes the safety, reliability, and availability requirements that distinguish OT from conventional information technology. Use those requirements to set the conditions for the review with operations. NIST SP 800-82 Rev. 3, Table 2.

Record the scope approver and the person who controls the work on shift. The scope approver signs the brief and approves any revision. The shift supervisor gives the go-ahead after checking the state of the plant against the brief. Give that supervisor explicit authority to stop the work. The reviewer and any worker who notices a concern can call for a pause. The plant retains authority over process safety, including when its emergency arrangements apply and who can direct activity on the line. The joint principles published by the Australian Cyber Security Centre put safety first in OT cyber security decisions. Principles of operational technology cyber security.

Name the evidence custodian too. This may be a controls engineer who knows which documents describe the installed line and which belong to a supplier’s earlier design. Give the custodian time to check record identity, revision, and suitability for release. If a record belongs to a shared service or a supplier, involve its owner before agreeing that the reviewer can see it. Procurement can record the commercial terms once operations and the evidence owners agree the limits.

Put the decision in one sentence that the reviewer can use when an ambiguity comes up. At a fictional food plant in Fribourg, plant manager Elise Rochat wants to decide whether the recovery records for packaging line 2 are adequate for planning a separate recovery review. She asks which copy the engineering team can tie to the current line, which changes the paperwork accounts for, and who would resolve any discrepancy. Alain Morel, the shift supervisor, controls the review window. Every name, date, and record identifier in the example is fictional.

Define the line and the records that describe it

Begin with the function and the physical boundary. Name the process, the line, and the assets represented in the records. Give each asset a site identifier or another reference that operations already uses. Where a supplier drawing calls a workstation by a different name, ask engineering to reconcile the names on paper. Two records with similar equipment labels can refer to different lines or to equipment removed during an upgrade. The joint asset inventory guidance recommends documenting OT assets and their dependencies and classifying assets by criticality and function. Foundations for OT cybersecurity.

For shared services, agree how far the reviewer may follow a dependency. In Fribourg, line 2 needs the site’s refrigeration service for the agreed production schedule. The line overview can record that dependency and identify its owner. The refrigeration equipment, its configuration, and its operating records are excluded. The same distinction applies to a supplier support arrangement. A maintenance ticket may establish who approved a particular visit and what work the supplier reported. Permission to read that ticket covers the named record. Any other supplier records need their own approval.

List the permitted methods alongside the systems they concern. In this brief the reviewer may read existing documents, inspect the named offline configuration copies as inert records, compare their metadata with the change register, and ask the custodian to explain differences. Use copies already held in the records repository and approved for this job. Agree a review location or controlled workspace that has no connection to the plant network. Confirm beforehand that the copies can be read there using the agreed method. If a copy requires a connection or execution to interpret it, log the limitation and ask for an approved documentary substitute.

Write the exclusions in words procurement and the shift team can apply. In Fribourg the brief excludes access to live controllers, operator stations, the engineering workstation, and the plant network. Scanning, live queries, supplier remote sessions, opening a project in a way that runs it, and all configuration changes are outside the commission. The reviewer may record a question about an excluded system and send it to the plant manager. Any work on that question needs a separate decision from the appropriate owner. Keep the original review narrow enough to finish with an honest account of its gaps.

Distinguish a correction to the brief from a request to extend it. If engineering corrects a spelling error in a line name, keep the original reference and record the correction so both parties can still recognise the asset. If engineering says a device was replaced and the old identifier now refers to equipment in storage, hold the affected work. The approver needs to decide whether the new asset and its records belong in the review. Check what the substitution changes about the assessed period and the conclusions that can be drawn. The reviewer needs the revised evidence list even when the work still takes place in the same office and within the same appointment.

Ask anyone proposing an exception to put the request in the scope record. Identify the question they want answered, the smallest change that would answer it, the records and owners involved, and any effect on staffing or timing. The approver can decline the request and leave the question open. If they approve a limited documentary exception, give it its own end time and identify who can act on it. When a supplier offers to explain a maintenance ticket, for example, let the approver specify the ticket and the participants. An invitation to discuss the ticket carries no permission to release more files.

State what each record can establish

Give the reviewer an evidence list with the purpose, date range, and permitted use for each item. Start with the engineering drawing and asset register to establish the documented boundary and the names used by operations. Add the change register and maintenance tickets to establish which work the plant recorded against those assets during the agreed period. Add the copy register and any existing recovery exercise record to see whether the plant can trace a saved configuration to a named asset and a known point in time. Joint guidance led by the UK National Cyber Security Centre notes that useful architecture information may already exist in configuration files and documentation. Creating and maintaining a definitive view of your OT architecture.

Treat the issue date, the event date, and the date of release to the reviewer as separate facts. A drawing signed this week can represent a layout from last year. A maintenance ticket closed yesterday may record work performed before the most recent copy was saved. Ask the custodian to confirm the date and revision that matter to the question in the brief. If the date on the register and the date associated with the copy differ, preserve both in the evidence notes and ask the custodian to explain the difference.

A copy register entry can support a finding that a copy was recorded for a named controller. An existing recovery exercise record can support a finding about the equipment and revisions used in that exercise. The reviewer should describe each finding at that level. A successful exercise for an earlier revision leaves recovery of the current revision unverified. Similarly, an access authorisation describes what the plant approved for a named person or role. A historical ticket may document a visit, but the current state of access is beyond what the ticket alone can establish. The Swiss National Cyber Security Centre addresses authorisation for external maintenance companies and configuration backups in its guidance on industrial control systems. Measures to protect industrial control systems.

Make the evidence list usable during a handover. For each item, include the record identifier, its revision or period, who released it, where the reviewer may read it, and the question it supports. When the reviewer cites it, include the page, entry, or date needed to find the basis for the finding. If the only basis is an interview, attribute the account and label it as such. Give the plant a way to correct an identifier without silently changing the evidence that underpins the draft.

Ask for the extent of the underlying record when the finding depends on an absence. One approved ticket for the period establishes that one ticket exists. If you want to know whether the copy register covers every recorded change since the last backup, ask the custodian which dates the register covers and whether any entries are still awaiting sign-off. A register extract that ends on 18 November leaves the 19 November work outside its coverage. If the custodian can explain why an entry is missing, cite that explanation and keep the documentary gap visible. The plant manager needs to know whether to request a better record or refer a substantive recovery question to engineering.

Limit disclosure at the same time as you limit the method. If the question is whether a supplier visit had written approval, a redacted ticket with dates, role, decision, and work reference may suffice. The custodian keeps the source record and approves the redaction. Keep sensitive operating details in the controlled workspace and agree what the report may reproduce. Include who can receive the report, how long the reviewer can retain the material, and who confirms that access has been withdrawn or copies disposed of. Send bidders the evidence categories and estimated number of records. Release individual files to the selected reviewer through the agreed channel.

Decide whether a maintenance window is needed

Ask the shift supervisor whether the permitted activities need protected time. Consider where the work happens, who has to leave normal duties to support it, and what happens if production or maintenance needs the same people. A custodian may be able to approve copies several days ahead. The reviewer may be able to read them away from the plant during normal office hours. If those conditions are enough, record that the work can proceed without reserving a maintenance window. State when operations staff are available to settle questions.

If the review needs the supervisor or controls engineer during production, agree whether to use part of an existing maintenance window or move the session. Find out what other work is booked and who has priority. A maintenance window belongs to operations. It provides a period in which the agreed records work can take place, subject to release by the supervisor. It gives the reviewer no authority over equipment or production.

Specify a date, start, and end in Swiss local time, together with a final time for raising questions and enough time for close-out. On the day, ask the supervisor to confirm the planned line state, the availability of the required people, and any competing work. Confirm that the reviewer has the approved evidence list and can identify the named workspace. If any condition is unmet, hold the review and record who will decide whether to reschedule. A booked time is a reservation. The supervisor’s recorded release is the permission to begin.

At the Fribourg plant, office-hours preparation covers the scope sheet, the index, and a check of the references by the evidence custodian. The operator reserves Saturday, 28 November 2026, from 08:00 to 10:00 CET for the review itself. The line already has a scheduled maintenance period. The space reserved for the review is an office, and operations expects the supervisor and controls engineer to be available for questions. Elise chooses the slot because production needs both people for a changeover on Friday. The review requires no additional line outage. At 09:45 the reviewer must stop raising new questions so the supervisor has time to close the session before the end of the window.

Settle what happens if the allotted time shrinks. If planned maintenance overruns and Alain is needed on the line at 08:00, the reviewer waits for his decision. A later start may be viable if there is still time to answer the agreed questions and finish the handover before 10:00. Name who can decide whether the shortened session is worth starting. In the example Alain can release the original scope during the reserved slot, with the same end time. Elise must approve any move outside the slot.

Write stop conditions and agree the calls

Write triggers that a tired person can recognise during a shift. In Fribourg, any line 2 alarm, an earlier restart, loss of the supervisor’s cover, receipt of an unlisted configuration, or a request for a connection to plant equipment stops the review. The end of the authorised window ends the session. An ordinary missing record can remain an evidence gap if the team can finish within the approved brief. An unexpected file described as a current configuration raises a different question because its provenance and handling have yet to be agreed.

When someone calls a stop, the reviewer stops the review and informs the shift supervisor using the site contact channel listed in the brief. The supervisor records the time, trigger, and last permitted activity. Record which item was open and what material the reviewer already received. If the concern is an unexpected file, leave it unopened, restrict its further distribution, and let the custodian and security lead decide how to handle it. If an alarm or safety concern is involved, operations applies the plant’s existing procedures. The reviewer makes their observations available as requested and leaves plant decisions to operations.

Make the escalation route depend on the event. An alarm goes straight to the shift supervisor. An unexpected file with no other signs of an incident goes to the supervisor and evidence custodian. Signs of possible unauthorised activity go to the supervisor and the plant’s designated incident lead through the internal response route. If the named supervisor cannot be reached, use the established duty control point and keep the session on hold. The designated incident lead decides with the responsible plant teams whether to activate incident procedures, retain evidence for the response, or refer the matter to the person responsible for external reporting. Swiss official guidance on industrial control systems calls for defined processes and responsibilities for incident management. Swiss National Cyber Security Centre guidance.

Agree what counts as resumption. The scope approver issues fresh written approval after reviewing the trigger, the remaining work, and the proposed time. If the trigger involved a safety concern, require confirmation from the plant’s designated safety authority before approval. The shift supervisor then gives a new release based on current conditions and records the time. An explanation for the alarm, a replacement file, or the return of a supervisor is information for that decision. If the approver cannot resolve the issue in time, close with the evidence reviewed and give the outstanding questions to their owners.

Use a scope sheet the shift can read

Keep a controlled copy of the approved sheet with operations and give the reviewer the same revision. Copy the fields below and substitute your own values. Keep the operational contact details in the plant’s controlled copy. The headings should tell the duty supervisor where to find the permission, the stop decision, and the person who can approve a change.

  • Decision and scope revision. FR-P2-01, revision 1. Elise Rochat will decide whether to commission a separate recovery review for packaging line 2.
  • Approvals. Elise Rochat, plant manager and scope approver, approved revision 1 on 26 November 2026. Nora Favre, site safety lead, confirmed the safety and staffing conditions. Alain Morel, shift supervisor, releases and stops work on shift.
  • Systems represented. Packaging line 2 controller P2-C01 and operator station P2-H01, represented by approved records. Refrigeration appears as a dependency on the line drawing.
  • Evidence and methods. Inspect drawing P2-D04 revision 3, copy record P2-B17 and its approved offline copy dated 12 November, change record P2-M42 dated 19 November, and recovery exercise record P2-R08. Compare record identifiers and dates in the controlled office workspace. Ask custodian Simon Blanc about discrepancies.
  • Exclusions and exceptions. Refrigeration records, other lines, live equipment and access, and all configuration changes are excluded. Changes to the approved record list, method, or time require Elise’s written approval.
  • Window and release. Saturday, 28 November 2026, 08:00 to 10:00 CET. Alain confirms the line state, staffing, and approved evidence list before release. Close new questions at 09:45.
  • Stop and escalate. Early restart, any line alarm, absent supervisor cover, unlisted configuration, request for live access, or window expiry. Stop and contact Alain through the duty control point. Route file concerns to Simon and suspected incidents to the plant’s incident lead.
  • Authority after a stop. Alain logs the reason and closes the session. Elise approves any revised brief in writing after the relevant confirmations. Alain gives a fresh release before work restarts.
  • Report and records. Deliver findings with record references and gaps to Elise and Simon by 12:00 CET on Monday, 30 November. Keep original records in the plant repository. Simon ends access to the original evidence packet at session close-out. The reviewer prepares the report from approved notes and returns those notes to Simon once Elise accepts the report.

Work through an incomplete review

On the Saturday, Alain confirms line 2 is idle as planned and releases the review at 08:00. Simon supplies the listed records. The copy record identifies the controller and accounts for the origin of the 12 November copy. The 19 November change record gives the same controller identifier and describes work after the copy date. The recovery exercise record refers to the previous revision. The reviewer records that the plant has a traceable copy for the earlier date. Two questions remain open. Which revision is current, and can the plant recover it?

At 08:35 a supplier sends a file described as the latest configuration. It is absent from the approved list. The reviewer stops without opening it and tells Alain what arrived, when, and through which channel. Alain records the stop and contacts Simon. Simon can establish whether the file came through a recognised release process and whether it refers to the same controller. A familiar sender or a convincing file name is insufficient to make it part of the authorised set. Simon also checks whether there is an existing copy in the plant repository with an approved record already attached to it.

Before Simon finishes, production asks to restart line 2 early. Alain closes the review at 08:50 and returns the available staff to operations. He records that the scope was held because of the file and that the early restart ended the opportunity to resume that morning. Operations manages the restart under its own procedures. The review record shows what the reviewer had read and what remained outstanding. It records the two events separately so the next approver knows both what needs to be resolved about the evidence and why the reserved window is no longer available.

On Monday, Elise can accept the bounded report and seek documentary follow-up. She asks Simon to reconcile the change record and the approved copy register before deciding whether to commission broader recovery work. Simon owns the search for a dated, approved record that covers the change. If he finds one, Elise can decide whether a short follow-up in office hours is sufficient and issue a revised brief with a new release. If no suitable record exists, she can record why the evidence is insufficient and refer the recovery question for a separate operations decision. The current report can be complete for the work performed even with that question open.

Commission the work against the approved brief

Ask bidders to confirm the exact scope revision in their quote. Request an estimate based on the listed records and named participants. Ask bidders to state how they would report a gap and how they handle a session that operations has to end early. Agree who covers the cost of a rescheduled session before booking time with the shift. If a quote assumes a visit to the line or access to its equipment, ask for the assumption to be removed from the quote for this commission. A proposed change to the commission returns to the plant approver.

At close-out, check that the report records the agreed decision, completed activities, evidence references, unresolved questions, and any stop or exception. Review every conclusion against the evidence it cites. Where the reviewer has relied on an older drawing or an incomplete change register, check that the date and limitation travel with the finding. Get an owner and follow-up date for each open question that affects the procurement decision. The plant manager can then accept the report as a record of bounded work and make a separate decision about what to commission next.

Once the operator has set the review boundary, the longer-term question is who maintains each control and produces its records when asked. Use the control ownership guide to assign those responsibilities. Assign owners to IEC 62443 controls and evidence.

If the records point to a separately owned web application, give its owner the boundary question and let them define a separate audit brief before procurement. Write a web application audit brief.

Put it into practice

Key takeaways

  1. 01Name the line and permitted methods in writing.
  2. 02Give the shift supervisor explicit stop authority.
  3. 03Require new approval when the agreed conditions change.

Sources

← Back to the blog

Frequently asked questions

Who can expand the scope during the review?

The designated plant approver records revised systems, methods, and timing before the reviewer proceeds.

What if an offline copy is out of date?

Ask operations to provide an approved replacement and flag the gap in the evidence.

Scope the release decision

Use the plant scope sheet to agree a review window with operations.

Deep Audit SprintDiscuss your scope