Short answer
Map industrial control requirements to the zones that contain the assets and the conduits that connect them. Assign an owner for each control and for each supplier handoff. Use ISA/IEC 62443 to structure the baseline, then keep evidence of who approves access, who maintains it, and when it is reviewed.
Before the next supplier maintenance window, decide who can authorise the work, who will perform it, and what record will show that the plant has taken back control. Put those answers in one matrix keyed to industrial zones and the connections between them. A ticket that says “vendor support complete” may settle a billing question. The shift supervisor still needs to know whether the approved person used the approved route, what changed on the line, and who confirmed that access ended.
An OT security engineer can assemble the matrix with plant operations, engineering, procurement, and the organisations that supply and maintain the equipment. Start with a decision the plant actually faces. For example, can an external technician use the maintenance connection for the next filling-line service, or does the work need to take place on site? The matrix gives the person making that decision a way to trace it to the relevant boundary, current records, and any open conditions. It also gives each party a specific obligation to price, schedule, or deliver.
Define the plant boundary before assigning controls
Describe the industrial automation and control system under consideration in terms of the process it supports. Name the site, line, operating states, and equipment included in the decision. Reference the current architecture drawing and inventory, with a revision and date. Include the plant-managed services on which the decision depends, such as the identity service for maintenance users or the repository that holds approved line configurations. If a service sits outside the boundary, identify its owner and the assurance you need at the interface. A box drawn outside the plant diagram can still affect whether the plant can approve a maintenance activity.
Use zones to group assets with common security needs. Record conduits for communications between zones. A zone name is a reference to a security boundary, so check what the group has in common before borrowing the name of a room or network segment. Record the purpose and endpoints of each conduit in scope. IEC 62443-3-2 connects this partitioning to system design risk assessment, target security levels for zones and conduits, and documented security requirements. Use the approved risk assessment as the source for those decisions in the matrix. IEC 62443-3-2:2020
For each supplier interface, write down the parties on both sides and the point at which responsibility changes hands. A conduit may carry a maintenance session, while the associated service contract covers who requests it and who sends the activity record. A supplier advisory, a support renewal, and a handover of configuration files are also interfaces for the worksheet. Give them their own identifiers and link them to the affected zones or conduits. This lets you track a missing supplier deliverable without treating every exchange of documents as an industrial communications path.
Name exclusions at the same level of detail as inclusions. If the review covers the filling line and its maintenance access, identify whether building services, other lines, and office administration are outside it. Keep any dependency that could change the decision visible. For example, you may exclude an enterprise identity platform from a plant review while still relying on its account revocation records. If a proposed activity would reach an excluded asset, send the scope back to the plant owner for review before the activity is authorised. For a separate decision on what an external reviewer may examine and under which plant constraints, use the guide to scoping an OT cybersecurity review.
Give each party the responsibility it can discharge
The asset owner assigns people who can make decisions about the operating plant. IEC 62443-2-1 addresses the policies and procedures of the asset owner’s security programme for an industrial system in operation. In the worksheet, identify which plant role owns each decision and who can deputise for that role. The network owner may own the approved conduit design, a shift supervisor may authorise a session within that design, and the plant manager may hold authority over an exception. Give each decision its own row if a different role can approve it. IEC 62443-2-1:2024
The service provider delivers the agreed integration or maintenance work and the records that show what it did. IEC 62443-2-4 covers security processes a service provider can offer for integration and maintenance of an automation solution. Distinguish the provider who hands over a configured system from the one who maintains it after commissioning. If the same firm does both, record which role produced each record. An integration handover might identify the configuration accepted at commissioning. A maintenance work note might identify the new revision and explain which part of that accepted configuration changed. IEC 62443-2-4:2023
The product supplier can account for the product and its support lifecycle. Ask the supplier to identify supported releases, product security capabilities, relevant limitations, and the channel through which it issues advisories. IEC 62443-4-1 concerns the processes used to develop and maintain a product securely. IEC 62443-4-2 concerns technical security capabilities of industrial components. In your matrix, distinguish the record about the supplier’s development or support process from the record about a capability of a specified component and version. Each supports a different review question. IEC 62443-4-1:2018 · IEC 62443-4-2:2019
For the configured system, ask the integrator how the design addresses the requirements assigned to the relevant zones and conduits. IEC 62443-3-3 addresses technical security requirements and capability at control-system level. Record the version and assumptions behind the integrator’s evidence, including services the plant supplies. The plant’s risk assessment sets the target. Product information describes what a component can do under stated conditions. The integrator’s as-built record describes what the installed arrangement provides, and the plant’s operating records show how that arrangement was used during the period under review. Keep those claims separate when deciding what evidence is sufficient. IEC 62443-3-3:2013 · IEC 62443-3-2:2020
One update can illustrate all four responsibilities. A supplier provides the release applicability and support conditions for a controller update. The service provider identifies the installed equipment affected and submits the proposed work and its consequences for the agreed system design. Plant operations decides whether the change fits the permitted production window and who can return the line to service. After the change, engineering reconciles the plant baseline against the handover record. Each party can complete its assigned work while another party still has an outstanding decision. A single row marked “patch managed by vendor” would hide those dependencies.
Set up a matrix that gives the reviewer a decision
Use a shared register or spreadsheet with an accountable editor. In its header, record the scope and its revision, the decision under review, the asset owner who can make it, and the date by which a decision is needed. Identify the authoritative risk, contract, and configuration records. Store evidence in the controlled location used by the parties. Put a reference in the matrix that an authorised reviewer can resolve, including which organisation holds the original where access is restricted.
Give each row a stable ID and a short statement of the control outcome. State the zone, conduit, or supplier interface and the lifecycle activity to which it applies. Name one role accountable to the plant for that outcome, the party that performs the work, and the party that produces the evidence. Name the reviewer who has authority to accept the evidence for the decision. Add the agreed source of the obligation, such as a plant requirement, a service schedule, or an approved design. Where your organisation has mapped requirements to a particular part and edition of IEC 62443, reference that mapping in the register. The example below uses local row IDs as worksheet references.
Write the evidence criterion so the reviewer can distinguish a record that exists from one that supports the decision. Include the artefact ID, revision or date, applicable assets or activity, and review result. Where the control concerns an event, add the event reference all parties can use. A service ticket and a session log may have different timestamps because the ticket closed after the session ended. The shared activity reference lets the reviewer match records without assuming two unrelated entries describe the same work. Agree on a time basis when records come from different systems, and state it in the review record.
Set a review trigger as well as a due date. An inventory row may be reviewed after an equipment change. A session close-out row comes due after each session, including one that ends early. The product support row should come back when the supplier changes the support position, even if the normal review date is weeks away. For each trigger, name the person who receives notice and who updates the row if the evidence arrives during a shift handover.
Use a small set of decision states. “Accepted” means the named reviewer accepted the identified evidence against that row’s criterion for the stated scope. “Open” means an action remains, with an assignee and due date. “Conditional” means the authorised risk owner agreed to a defined temporary operating condition and linked the exception record. Use “outside scope” with a reason and a reference to the owner of any material dependency. Acceptance applies to the claim on the row. A line inventory accepted last month can still be the wrong basis for a change if a controller was replaced yesterday.
Agree how the matrix records evidence that covers a sample. If the supervisor has reviewed one maintenance session, record which session and which parts of it the review covered. Where the decision depends on the current state of all supplier access, ask the responsible owner for a record covering that population. The old session can show how the close-out process worked on a given date. A current access record answers a different question. This distinction matters when the team reviews several lines together and one plant’s past work record appears in a report covering the whole site.
Fill the matrix for a maintenance decision in Valais
A fictional Valais beverage plant is preparing a planned service to investigate intermittent faults on its filling line. The maintenance firm asks to review line diagnostics remotely. The plant’s operations manager must decide on 12 November whether the 17 November work can use remote access. The shift supervisor can authorise an individual session within the approved arrangement. The plant manager holds authority for temporary risk exceptions. All dates, references, and records below are illustrative.
The scope is revision 4 of the filling-line boundary. The plant calls its filling-line zone Z1, its office zone Z2, and its maintenance access zone Z3. Z1 contains the controllers and operator stations in this service scope. Z3 contains the plant-managed entry point for supplier access. The approved maintenance conduit, C1, connects Z3 and Z1 for the defined support purpose. C2 is a separate reporting conduit between Z1 and Z2. It carries production reporting and has a different approval owner for the office-side data use. The service decision covers C1. C2 is recorded because a change to access for one purpose must preserve the boundary governing the other.
The equipment supplier’s advisory and support interface is I1. The maintenance firm’s access request and close-out interface is I2, linked to C1. H1 is the integrator’s handover of the deployed configuration. The plant excludes the office estate beyond the reporting endpoint and all other production lines. It records the enterprise identity service as an external dependency because workplace IT holds the records needed to confirm whether a maintenance identity is still enabled. Safety functions follow the plant’s separate approval process. The proposed diagnostic work has no approval to change them.
The compact example below gives each record a decision and a next review point. In a working spreadsheet, give the evidence producer, evidence reviewer, date, status, action assignee, and next trigger separate cells so you can filter by party or due date.
- Z1-01 · Z1 · inventory.
- Outcome and accountable plant role. The line inventory matches the approved equipment record. The automation lead owns it.
- Line engineering reconciles the records and issues the inventory revision.
- Evidence, reviewer, and next decision. Inventory-04, dated 5 November, identifies the controllers and operator stations. The automation lead accepted it on 6 November. Review after any replacement or version change.
- Z2-01 · Z2 · reporting endpoint.
- Outcome and accountable plant role. The office-side endpoint has a named owner and a current inventory entry. The workplace IT lead owns it.
- Workplace IT maintains the office inventory and provides the endpoint record.
- Evidence, reviewer, and next decision. WIT-09, dated 5 November, links the endpoint to C2. The workplace IT lead accepted it on 6 November. Review on endpoint or ownership change.
- C1-01 · C1 and H1 · system design.
- Outcome and accountable plant role. The installed maintenance arrangement matches the approved design. The plant network owner owns the conduit.
- The integrator provides the as-built handover. The plant network team maintains the approved record.
- Evidence, reviewer, and next decision. Drawing D-04 and handover H-04, dated 5 November, cover Z3 and Z1. The network owner accepted the baseline on 6 November. Review if the requested route, endpoints, or purpose changes.
- C2-01 · C2 · system design.
- Outcome and accountable plant role. Production reporting retains its approved purpose and boundary. The plant network owner owns the conduit.
- The plant network team maintains the connection record. Workplace IT confirms office-side use.
- Evidence, reviewer, and next decision. CR-02, dated 5 November, records both owners and the reporting purpose. The network owner accepted it on 6 November. Review on any change in direction, endpoint, or purpose.
- Z3-01 · Z3 · operating access.
- Outcome and accountable plant role. Plant records identify the supplier access authorised for the decision period. The workplace IT lead owns the identity dependency.
- Workplace IT provides the entitlement record. The access custodian reconciles it with the plant approvals.
- Evidence, reviewer, and next decision. AR-06, dated 10 November, identifies the agreed maintenance access population. The workplace IT lead accepted the reconciliation that day. Review after any session or maintenance personnel change.
- I2-01 · C1 and I2 · session approval.
- Outcome and accountable plant role. The maintenance request identifies the person, purpose, and window. The shift supervisor owns the session decision.
- The service provider submits the request. The shift supervisor records the decision.
- Evidence, reviewer, and next decision. SR-217, received 10 November, covers the 17 November visit. Approval is open pending the operations manager’s 12 November access-method decision and closure of I2-02.
- I2-02 · C1 and I2 · session closure.
- Outcome and accountable plant role. The plant can reconcile the last approval and the end of access. The shift supervisor owns closure.
- The service provider submits the work note. The plant access custodian and workplace IT provide records of access ending.
- Evidence, reviewer, and next decision. SR-204 has an approval and work note dated 29 October. The matching close time is missing. Open on 10 November. The access custodian owes the record by 12 November for supervisor review.
- I1-01 · I1 and Z1 · product support.
- Outcome and accountable plant role. The plant knows the support position for the installed controller release. The automation lead owns the plant decision.
- The product supplier issues the support notice. Line engineering maps it to the installed release.
- Evidence, reviewer, and next decision. PS-11, received 9 November, confirms support for the release in Inventory-04 and lists diagnostic limitations. The automation lead accepted applicability on 10 November. Review on release or supplier notice change.
- I1-02 · I1 and Z1 · product lifecycle.
- Outcome and accountable plant role. Plant engineering knows how the supplier distributes security advisories for the installed product family. The automation lead owns the plant subscription.
- The product supplier provides the advisory channel and escalation contact. Plant engineering records receipt and assigns a deputy.
- Evidence, reviewer, and next decision. PS-12 and engineering record Advisory-03, dated 9 November, identify the product family and contact. The automation lead accepted them on 10 November. Review at support renewal or contact change.
- I1-03 · I1 and Z1 · component capability.
- Outcome and accountable plant role. Line engineering knows which named operator roles the installed station release supports. The automation lead owns the plant requirement.
- The product supplier provides the versioned role description. The integrator records the roles assigned in the installed configuration.
- Evidence, reviewer, and next decision. PS-13 identifies the product capability. H-04 records the installed role assignment. The automation lead accepted the comparison on 10 November. Review when either the release or the assigned roles change.
- H1-01 · H1 and Z1 · operational handback.
- Outcome and accountable plant role. The plant can trace the resulting configuration and release the line. The shift supervisor owns handback.
- The service provider records work and any change. Line engineering reconciles the baseline.
- Evidence, reviewer, and next decision. Work-217 awaits the 17 November service. The supervisor requires the signed work record and the engineering disposition before accepting the handback.
Use the evidence to decide the access method
At the review on 12 November, the operations manager sees a supported controller release and an accepted system design for C1. The maintenance request also identifies the technician and the purpose. Those records answer the product, design, and request questions. They leave an operating question open. The October approval for SR-204 and the provider’s work note both exist, but the provider’s note records the end of work. The plant needs evidence of when access ended and whether the account authorisation was withdrawn as expected.
The access custodian and workplace IT confirm the previously assigned access is now absent, using a dated access record. The confirmation answers the question about current entitlement. The original close time remains unresolved. The supervisor attaches the new record to I2-02 and keeps the historical discrepancy open, with an assignee and a date to establish what the retained records can support. If the historical timestamp cannot be recovered, the supervisor records the missing evidence and refers the decision on future use to the operations manager. The operations manager can require a corrected close-out arrangement before reconsidering remote work.
On 12 November, the operations manager records decision D-217 to proceed with supervised on-site service on 17 November, subject to the usual plant work approval. The plant confirms that the provider can do the agreed diagnostics on site. The shift supervisor closes the remote request as declined for this window, links it to D-217, and keeps Work-217 open for the on-site handback. The access decision governs this activity. The network owner reviews the design record if a later request changes the route, endpoints, or purpose.
Procurement asks the maintenance firm to add a close-out deliverable to the service schedule. It must quote the same activity reference used by the plant, identify actual work and any configuration change, and reach the shift supervisor within the agreed handover period. The plant assigns separate responsibility for supplying plant access records and resolving an unmatched entry. These obligations give the next reviewer something concrete to check. If the provider cannot supply its part of the record, the plant can price on-site support or reconsider which service it buys.
Record exceptions with a decision date and an end condition
Treat a departure from the agreed baseline as its own decision. Suppose the Valais plant later receives a product notice saying the installed controller release is approaching support withdrawal, and the replacement requires a longer outage than the next maintenance window permits. Link the notice to I1-01, identify the affected release and assets, and open a plant risk decision. Ask the service provider to describe the implications for maintenance and the affected system interfaces. Operations can then compare continued use within defined conditions with an earlier replacement outage.
IEC’s public description of 62443-2-1 acknowledges that older systems can lack native security capabilities and that an asset owner’s policies and procedures can cover compensating measures. For a temporary exception, specify which requirement the plant is departing from, what exposure remains, which conditions apply, and who can authorise it. A supplier can explain product constraints, and the service provider can deliver assigned measures. The plant risk owner signs the plant’s decision and names the evidence needed to keep it in force. IEC 62443-2-1:2024
A usable exception record gives the affected row IDs, the reason, the allowed activity, the owner of each condition, and the evidence of each review. Give it an expiry date and an earlier reopening trigger, such as a change in the supplier’s support position or a missed outage. State what authority applies at expiry. If the authorised period ends before the replacement is accepted, the plant owner needs a fresh decision for continued use. Keep the original risk record and link the new decision so reviewers can reconstruct who authorised which period and conditions.
In a later review at the same fictional plant, the product supplier gives 31 January as the last day of support. The planned replacement outage is 14 February. The plant’s baseline calls for a supported release on Z1, so the automation lead records the interval that would fall outside it. Without product support, the plant may have to respond to a new fault or security notice without a supplier fix. The service provider confirms that the planned replacement depends on delivery of a compatible unit. Procurement logs the delivery commitment so operations can see when the alternative outage date becomes uncertain.
The plant manager records exception EX-06 against I1-01 and Z1-01 on 20 January. It covers ordinary production on the existing configuration for 1 to 14 February, with supplier work limited to supervised on-site activity under separate work approval. The automation lead reviews supplier notices and the delivery commitment each week and dates the review in EX-06. A notice affecting the installed release or a slip in delivery brings the decision back to the plant manager that day. The exception expires at the end of 14 February. Continued use after expiry requires the plant manager’s decision under the plant’s operating authority. The automation lead closes EX-06 after the replacement release appears in the accepted inventory and the shift supervisor records handback.
If the plant receives a generic supplier statement that the product family remains supported, the automation lead compares it with the notice for the installed release. Where the documents describe different scopes, the release-specific date still governs the decision until the supplier confirms otherwise. The maintenance firm can report that it can continue its contracted service during the interval. Record that as service availability. The product support row needs a statement covering the installed release, and the exception remains the record for the plant’s decision to operate.
Guard the scope at the decision point. A request to add a second line, use a new support route, or change the production purpose belongs in change review because it affects the agreed boundary. Update the scope and review the relevant risk and system records before accepting the new arrangement. Keep plant work permits, process safety decisions, and authorisation for technical assessment in their respective plant processes. The matrix records the references and owners a reviewer needs for the decision at hand.
Agree how evidence passes between organisations
When you buy a service, put the evidence obligations in the same schedule as the work. Specify who delivers the record, when it is due, who accepts it, and which systems or releases it covers. Ask whether the maintenance firm relies on a subcontractor or on information from the product supplier. If the provider needs a supplier advisory before it can assess applicability, give that dependency a named contact and a decision deadline. Agree how late evidence is handled when the plant has to commit to an outage before the supplier replies.
Several parties may hold pieces of one record. Agree which identifiers they share, what can be redacted, and who may view supporting material under restricted access. A supplier might allow a plant reviewer to inspect a support record without distributing a copy to shift staff. In that case, record what the reviewer saw, the relevant version and date, and the conclusion the reviewer could draw. If the restriction prevents a reviewer from confirming applicability, leave the line open and record exactly which fact is missing. Keep operationally sensitive detail in the controlled evidence store.
Give handover evidence an owner for the period after a contract ends. A new maintenance firm needs the accepted baseline and the records that explain interim changes. The outgoing provider may still hold a work note that the plant needs for a review. Procurement can specify the transfer format and date, while plant engineering checks which revisions the incoming provider receives. Link the access closure to that handover so the plant can establish when each provider’s authority began and ended.
If you maintain an organisation-wide control catalogue, map its control IDs to the local rows so central reporting can find the plant evidence. Keep the local zone, decision owner, and acceptance condition attached to each row. If you are still deciding which catalogue should supply those shared IDs, see the guide to choosing a security control framework. For a Swiss electricity grid operator that also needs sector-specific control evidence, use the guide to ICT controls for Swiss grid operators for that separate decision.
At the next maintenance planning meeting, select the rows that govern the proposed work. Ask the shift supervisor to identify the approval record they need, the service provider to confirm when its work note will arrive, and the access custodian to identify the record that will establish closure. Assign a due date for any missing item. Record the chosen access method alongside the scope revision and the rows that support it, so the person taking over the next shift can act on the same decision.
Put it into practice
Key takeaways
- 01Map each zone and connection to an accountable owner.
- 02Make supplier access approval and closure observable.
- 03Attach dated evidence to the baseline.