Assess ICT controls for a Swiss electricity grid operator

Compare required and observed scores for your grid operator class. Separate control room and office IT evidence, then assign an owner to each gap.

Swiss Cyber Security19 min readPractical readingStart reading ↓

Short answer

For a Swiss electricity grid operator, first identify the category by annual electricity transported in its grid area. Then use Annex 1a of the Electricity Supply Ordinance to compare the applicable minimum score for each task with your observed score. Record the evidence and assign any gap to a named owner.

Start with the annual electricity transported in your grid area. Use that figure to establish the operator’s category, then look up the minimum for each applicable task in annex 1a of the Electricity Supply Ordinance (StromVV, SR 734.71). Record what your evidence supports today beside the minimum. Give each shortfall an owner, a due date and a check that will show whether the correction worked. The result is a working record your control-room and office IT teams can use to reconcile their self-assessment before completing ElCom’s Monitoring Cyber survey. Fedlex, StromVV, consolidation of 1 July 2026, art. 5a and annex 1a · ElCom, Monitoring Cyber instructions, February 2025

Article 5a paragraph 1 letter a and annex 1a points 1.1 (grid operators) and 1.2 (qualifying providers) must be read together. In the consolidation dated 1 July 2026 the German and French tables give A ≥450, B ≥112 and <450, C <112 GWh/year. The Italian table prints B ≥112 and ≥450, C ≥112, and article 5a paragraph 1 refers to annex 1. The worked examples use the German and French intervals as assumptions. Where the discrepancy affects your classification, document the activity and volume and seek clarification from ElCom before relying on the class. Fedlex DE · Fedlex FR · Fedlex IT

Establish which activity you are assessing

Article 5a makes the recommendations of the May 2023 minimum standard for improving ICT resilience binding at the applicable protection level in annex 1a. The article took effect on 1 July 2024. Paragraph 2 expressly leaves the internationally recognised standards cited inside the ICT minimum standard non-binding. Paragraph 3 requires the undertaking to demonstrate to ElCom, on request, that it has reached the applicable protection level. Annex 1a sets minimum values for individual tasks insofar as they apply. A certificate covering some of the same controls may point you to evidence. You still need to assess the relevant tasks and substantiate their scores under the Swiss rules. Fedlex, StromVV, 1 July 2026, art. 5a and annex 1a

Grid operator category Electricity transported in its grid area
A At least 450 GWh per year
B At least 112 GWh and below 450 GWh per year
C Below 112 GWh per year

At exactly 112 GWh per year the grid activity is B. At exactly 450 GWh it is A. Preserve the precision of the underlying figure when it is close to either boundary. The measure is annual electricity transported in the grid area. Retail sales volumes, the capacity of a substation in MW and the group’s total electricity purchases answer different questions. An energy trader that only sells electricity has no grid operator activity on that fact alone. For the survey, the grid operator enters its transported electricity in the main form. Fedlex, StromVV, 1 July 2026, annex 1a, no. 1.1 · ElCom, Monitoring Cyber instructions, February 2025, main form

For your internal classification record, ask the person responsible for energy accounting to provide the dated source, reporting period and network boundary. Keep the calculation in its original units and record the conversion. A return of 86,000 MWh is 86 GWh. Keep a reference to the underlying return so a second reviewer can reproduce the figure. Where two reports disagree, compare the areas and periods they cover before choosing a value. A change of operator partway through the year or a change in the area covered can make a familiar report unsuitable. Record the unresolved point and have the person responsible for regulatory submissions check it against the applicable survey instructions before confirmation.

A group that both operates a grid and generates electricity needs a separate scope decision for generation. Article 5a covers non-nuclear producers and storage operators if they operate facilities totalling at least 100 MW and can control them through one system. For those activities, the annex sets A from 800 MW and B from 100 MW up to but below 800 MW. There is no category C for these activities. Consider a fictional business that operates a grid carrying 86 GWh per year and controls 120 MW of non-nuclear generation through one system. Its grid activity is C and its generation activity is B. Keep two assessments. An inventory export from a shared system can support both if the assessor can identify which records and processes substantiate each answer. Fedlex, StromVV, 1 July 2026, art. 5a para. 1 and annex 1a, nos. 1.1 and 1.3 · ElCom, Monitoring Cyber instructions, February 2025, questionnaire selection

Check who has permanent control of grid assets

Article 5a paragraph 1 letter c covers providers that can permanently control grid operators’ installations. Annex 1a uses the volume of transported electricity accessible through one system to assign such a provider to A, B or C, at the same GWh thresholds as for grid operators. The figure for the provider therefore follows the accessible scope of its control system. A provider with permanent control of installations in two areas accessible through one system, with 65 and 70 GWh per year of transported electricity in scope, would be B in this hypothetical case. Each customer establishes its own grid category. If control is split between systems, establish which installations and volume are reachable through each before drawing a classification conclusion. Client counts and the volumes across all contracts cannot substitute for that work. Fedlex, StromVV, 1 July 2026, art. 5a para. 1 let. c and annex 1a, no. 1.2

Separate what the contract says from what the service actually enables. A supplier that sells equipment, handles invoices or receives read-only status information lacks the control capability described in the grid-provider provision on those facts. A technician authorised for a particular maintenance visit, with control confined to that visit, has a different remit from a standing control service. A control function available on a permanent basis warrants assessment even if operators seldom invoke it. For a disputed case, have the service owner document the standing permissions, the need for operator authorisation, the systems in scope and whether the provider can issue control commands under the actual operating arrangement. Record both the scope conclusion and the facts that would trigger reassessment at renewal.

Providers of control services to qualifying non-nuclear generation or storage installations have a separate test. They must be able to control the installations permanently and thereby have access, through one system, to at least 100 MW. The same 100 MW and 800 MW cut-offs in the annex determine B and A. Nuclear power plant operators are excluded from the generation limb. A supplier with permanent control of 60 MW through one system does not qualify under that generation or storage provider test on those facts. Check a separate grid control service on its own facts. In Monitoring Cyber, select the questionnaires for the relevant activities, including the relevant provider activities. The main form asks grid service providers for the affected grid areas and the electricity transported. Fedlex, StromVV, 1 July 2026, art. 5a para. 1 let. c and annex 1a, nos. 1.2 and 1.4 · ElCom, Monitoring Cyber instructions, February 2025, questionnaire selection and main form

Keep access to the proof in the procurement decision. Ask a provider to name the person who can supply dated inventory records, show how updates reach the operator and explain what is available after the contract ends. For a maintenance contract where the provider falls outside the permanent-control provision, the operator can still depend on it for records about replaced equipment. Make that handover an acceptance condition for the service. For a standing control service, obtain evidence for the operator’s own assessment as well as checking the provider’s obligations. Agree who resolves conflicting records so that each organisation can explain what its own score covers.

Assign a minimum and an observed score to each task

Read the task in the May 2023 ICT minimum standard and take its minimum from your category’s column in annex 1a. ID.AM-1 concerns the process for keeping the ICT asset inventory complete. In the survey it is the hardware inventory line. ID.AM-2 covers the inventory of software platforms, licences and applications. The ElCom guide shows the two tasks as separate lines and has separate fields for operational technology (OT) and information technology (IT). Record what each score covers. If a system supports control-room operations and office functions, document the dependency and how you treat the system in each assessment. Federal Office for National Economic Supply, ICT minimum standard, May 2023, section 2.2.1 · ElCom, Monitoring Cyber instructions, February 2025, questionnaire fields

Applicable task A minimum B minimum C minimum
ID.AM-1, ICT asset inventory process 4 3 3
ID.AM-2, software inventory 4 3 2

The scale in section 3.1.1 of the minimum standard describes task implementation. At 0 the task has yet to be implemented. At 1 it is partly in use and still lacks full definition or acceptance. At 2 it is partly in use under a fully defined and adopted process. At 3 it is fully or largely in use as an established practice. At 4 it is adaptive, with continuing review and improvement. A defined process and a recent export can help demonstrate 2 when coverage is partial. To substantiate 4, show how recurring review has changed the process and how the team checked the effects of the changes. The scale differs from an organisation-wide maturity tier. An observed 4 on an office software task cannot offset a 2 on operational hardware when that task requires 3. Fedlex, StromVV, 1 July 2026, annex 1a, no. 2 · Federal Office for National Economic Supply, ICT minimum standard, May 2023, section 3.1.1

Assess applicability before judging the observed score. A dash in the annex means the column specifies no minimum for that task. For instance, ID.AM-4 has no specified minimum in category C. ElCom’s guide directs users to select the form’s n/a option where category C carries no particular requirement for a point. A project that has yet to implement an applicable control, or an operator unable to retrieve the documents behind a proposed score, needs a different entry. Record the implementation state or evidence gap and have the assessor resolve any uncertainty before the form is confirmed. Both inventory rows in the table have category C minima. Fedlex, StromVV, 1 July 2026, annex 1a, no. 2.1.1 · ElCom, Monitoring Cyber instructions, February 2025, control point assessment

Review a fictional 86 GWh grid in Valais

At a fictional Valais operator, the risk lead takes the annual energy-accounting return to a joint review with the grid asset lead and the control-room supervisor. A signed internal note records 86,000 MWh for the operator’s grid area in the reporting year. The risk lead enters 86 GWh and category C in the working record. The team starts with the two OT inventory rows because a year’s worth of remote substation replacements has been documented on handover sheets. Some of those changes are missing from the central record. The examples and document references below are fictional.

Task and domain Required Observed Evidence reviewed Decision and owner
ID.AM-1, grid OT 3 2 Hardware export HW-10, approved inventory procedure and handover comparison HW-11 Grid asset lead reconciles remote substation handovers by 15 March
ID.AM-2, grid OT 2 2 Software export SW-04, adopted update procedure and maintenance comparison SW-05 Control-room supervisor retains the evidence and tracks remaining coverage in the next review

For hardware the team compares the register with records from a site refurbishment and an equipment replacement under routine maintenance. The refurbishment appears in the register. The maintenance work is signed off in the field, but the replacement unit is missing and the retired unit still appears as live. A separate handover shows that an entire remote location was omitted from the import. The process is documented, approved and working at the main sites. The scale supports 2 in the example because implementation across the assessed estate remains partial. The team can explain that judgement without claiming a percentage of completion or treating the few checked records as representative of every site.

The software register covers the control-room platforms and applications maintained on the usual service cycle. The owner compares the inventory against recent changes and verifies the recorded versions and application ownership for the sampled entries. The review also identifies software in engineering use that has yet to be fully brought under the register. Because the process is defined and adopted and the coverage is partial, the assessor records 2. That meets this row’s C minimum. The same observed score would leave a shortfall in B or A. The control-room supervisor keeps the incomplete coverage visible even though the row meets its annex minimum.

On the office side, the risk lead asks IT for its own proof. The office device register may have a routine feed and a process for closing entries after collection of equipment. The control-room supervisor has different inputs, often from maintenance contractors or commissioning teams. Compare each set with independent records from the same period. If an office-managed device also supports an operational workflow, agree which team keeps the primary record and how the other team learns of changes. The scoring owner needs to see where the process runs and what it covers before copying any value into a survey field.

Agree how records move between the field and the control room

Choose a starting population for the hardware review that exists independently of the register. The fictional team uses the list of sites for which it has received maintenance or commissioning records. A sample drawn entirely from the inventory can show whether known records are accurate, but it can miss sites that never entered it. In the other direction, start with a few rows marked in service and ask for their latest handover or operating record. The two directions reveal different failures. Document the kinds of sites or changes sampled so that a later reviewer knows whether the check extended to equipment maintained externally.

Treat a move between locations as a single change in the inventory process. When the operator receives a spare into stock, it can record the item and its status. If a crew puts it into service during a call-out, the handover must identify the new location and the unit removed. If the workshop subsequently repairs the removed unit and returns it to stock, the record can show that third state. A process that updates only new purchases loses sight of both devices even when every invoice is correct. The sample can follow one such transition from the crew’s work order through to the status confirmed by the register owner.

For the software review, nominate a person who can explain the difference between entitlement and deployment within the sampled scope. An invoice can show that the operator bought a licence. A release note or change record for a control-room workstation can show what was deployed and when. The software owner’s records can link the two where that relationship matters. At the fictional operator the first export uses inconsistent names for one application across two maintenance records. The reviewer checks the records with the application owner, documents the mapping and leaves an open item where the version cannot be confirmed. This gives the next reviewer a question to resolve and avoids turning a guess into a lasting inventory entry.

Decide which record prevails for each field. Operations can confirm that a device has entered service. Purchasing can account for the equipment delivered against an order. A supplier’s maintenance report may identify a replacement before either internal system reflects it. When two sources use different identifiers, keep a cross-reference and ask someone with authority over the asset to confirm the match. The person reconciling the inventory needs a way to record an unresolved match and route it for decision. Otherwise the pressure to complete a spreadsheet makes it likely that duplicate or uncertain items will disappear from view.

Agree how to handle time between snapshots. A dated export shows what the inventory contained on that date. A reconciliation completed the following week may reflect changes after the export. Keep the cut-off clear so that the assessor can tell whether a newly discovered gap belongs to the survey period or arose later. If a project is partway through migrating the records, preserve the old evidence and track which sites have passed their checks in the new process. That distinction will matter if ElCom asks about a result submitted before the migration completed.

These are internal review methods. Choose checks that reflect how your team receives, changes and retires equipment and software. In a small utility, the evidence might be a handful of signed handovers, an adopted procedure and controlled inventory exports. The useful test is whether someone outside the original review can follow the finding from the source record to the resulting score and back again.

Buy the work that closes the shortfall

The immediate buying decision in the Valais example is whether to commission a targeted reconciliation or procure a new inventory platform. Start with where the gap occurs. The main register accepts changes from refurbishment projects. Routine maintenance handovers fail to reach the person who maintains the register. A targeted work order can address both the missing historical records and the handover step. Ask the bidder to show how it will trace a commissioned unit through to a corresponding live register entry, how it will account for retired units and how the operator will handle the next maintenance change using its own staff.

In the fictional work order, the asset lead supplies the site list and change records. The contractor returns a versioned reconciliation with a disposition for each mismatch, identifies points it could not verify and trains the regular register owner on the resulting routine. The operator samples a maintenance event that occurred after the reconciliation began. A successful check follows the work record to the updated register and identifies who confirmed the change. If the previous omissions can recur on the next call-out, the handover still needs work. Keep the score supported by the evidence at the assessment date until a repeat review justifies changing it.

Where a platform purchase is under consideration, compare what each supplier can deliver on the same limited set of records. Have it demonstrate how you can export an auditable inventory, retain changes and assign exceptions for human review. Check whether field handovers and licensed applications can be represented with the records available to the operator. Ask how the operator retrieves dated exports if the subscription ends. Keep the acceptance test and the operator’s decision to change its observed score separate. One concerns a supplier’s deliverable and the other covers how the task operates across the assessed estate.

Avoid making access to live equipment a condition of a proof of concept. The operator can usually test import, reconciliation and export using controlled extracts or a test environment provided for the exercise. If a reviewer must confirm equipment in the field, use the operator’s existing maintenance and safety procedures. Agree with the control room who authorises any on-site check and when it can take place. Under the work order, access to source records should be proportionate to the deliverable and identifiable in the handover notes. This lets the buyer verify coverage and document availability without disrupting normal operation.

For category A, purchasing a system with scheduled reports would leave a separate question about adaptation. Ask the team to explain what it does when reviews uncover missed assets or stale software records. An observed example could be the revision of the commissioning handover after a recurring omission, followed by a check on later handovers to see whether the error stopped. Save the original finding, the approved adjustment and the follow-up result. This is the kind of evidence that can support the continuing improvement element of a 4 when the underlying task is implemented. It is an example of internal evidence design, with the scale itself defined by the minimum standard. Federal Office for National Economic Supply, ICT minimum standard, May 2023, section 3.1.1

Prepare the survey and keep the underlying proof

The February 2025 instructions describe the first survey workflow. In May 2026 ElCom said it planned the next round for 2027, with a simplified questionnaire for protection level C and an Excel upload option. Check the instructions for the actual round before relying on the earlier screens. ElCom, grid operator briefing, 12 and 19 May 2026, p. 76

Under the February 2025 workflow, complete each relevant activity questionnaire and then the main form. For each task, enter the maturity values for OT and IT in the respective fields. Where a lower than required value has a planned measure, the guide provides a measure field for the corresponding domain and calls for an upload of the implementation plan. It also allows a short comment. A draft can be saved before confirmation. Check the activity statuses in the main form and confirm the completed survey after verifying the entries. Use the invitation and instructions for your survey period to confirm practical details such as timing and access. ElCom, Monitoring Cyber instructions, February 2025, assessment and final submission

Build the internal evidence record so another person can explain the answer when the assessor is unavailable. For each result, keep the activity, category, task, IT or OT scope, applicable minimum, observed score, assessment date and rationale. Add a stable reference to the dated inventory, the procedure and a record of the review. Where there is a shortfall, record the responsible person, the work they will do, the due date, and which result will demonstrate completion. Keep the original answer and the subsequent reassessment in separate versions. Dated records let you show that the new value corresponds to a change in the control.

Give the evidence a level of detail proportionate to the decision. A management review can often use a short finding and an identifier for the restricted original. The people validating the score need access to the underlying evidence. Where disclosure is needed, the staff member handling regulatory submissions should check what ElCom has requested and use the appropriate channel. In the fictional Valais case, a short index would point first to the energy return and the category rationale, then to the two separate task judgements and finally to the action plan for the hardware gap. A date and a person responsible for retrieval make each reference usable.

ElCom describes self-assessments as one element of risk-based supervision. The regulator can also seek information and review implementation. The obligation to demonstrate the relevant level on request comes from article 5a paragraph 3. A submitted self-assessment or a planned measure describes your position at a point in time. Where a score sits below the annex minimum, the shortfall remains until the applicable level is achieved. Keep the plan and the later proof together so the person replying to a request can distinguish the submission date from the actual date of correction. Fedlex, StromVV, 1 July 2026, art. 5a para. 3 · ElCom, Directive 1/2024 on cybersecurity supervision, updated 1 April 2025

Before the next review, bring the annual electricity figure, one recent control-room equipment change and one software maintenance record. Have the owners trace each change into its inventory and record what they can substantiate. Ask whose name goes against any open correction and what they will bring back at the due date. With those two rows complete, apply the same method to the other relevant tasks and domains. The first review should leave the risk lead with a defensible score for each sampled row and a decision about any work that still needs to be done.

Put it into practice

Key takeaways

  1. 01Classify the grid activity using transported electricity.
  2. 02Determine the minimum separately for each applicable task.
  3. 03Link each score to evidence you can produce.

Sources

← Back to the blog

Frequently asked questions

Can I copy the hardware minimum into the software row?

Use ID.AM-2. Its category C minimum is 2. The ID.AM-1 minimum is 3.

What if we carry out several activities?

ElCom's instructions let you select multiple applicable questionnaires.

Scope the release decision

Take a dated inventory sample to the next Monitoring Cyber review.